Capital Development
SITE MASTER PLAN
As a part of this project, the overall Site Master Plan has been reviewed and updated to ensure the master plan reflects the Colleges’ developing educational requirements, ethos, values and aspirations.
Completed Master Plan Stages
Stage 1 – Completed for the 2014 school year
Junior School
New Kindergarten to Year 2 Classrooms, Covered Area, Multipurpose Areas, Temporary Library, Temporary Administration; external works; hardcourts; and Car parking.
Stage 2 – Completed for the 2016 school year
Junior School
New Year 3 - 6 Classrooms, new Multipurpose building; new administration Building, conversion of temporary facilities; car park extensions; and external works.
Stage 3- Completed for the 2018 school year
Secondary School
South wing of the new Learning Block, New playing Field, External hardcovers, carpark extension and external works and service
Stage 3a- Completed for the 2019 school year
Secondary School
North wing of the new learning block, New Resource/ Science Building, New administration building, temporary grounds, and Maintenance facilities, and external works
Stages 4-5 - Completed for the 2023 school year
Secondary School
New Visual and Performing Arts building (originally in stage 4), new Technologies building, new maingate facilities and compound, external works and services.
Stage 6 - Completed for the 2024 school year
Secondary School
New gymnasium; new classrooms (to cater for year six moving to the middle school); New hardcourts, new playing field; car park extension; external works and services.
Future Master Plan Stages
Stage 7- Complete for 2026 school year
Junior School
New junior school multipurpose building; external works and services
Secondary School
New theatre building; hardcourts; carpark extension; external works and services.
Stage 6 Gymnasium (2024 completion)